ADDWORKINGDAYS{...} -- add working days to date

  • Calculates the day that is a number of working days later or earlier then a given date
  • Syntax: %ADDWORKINGDAYS{"format" date="date|$variable" delta="days" holidays="comma separated list of dates"}%
  • Supported parameters:
    Parameter: Description: Default:
    "format" Format of the displayed date. Time is always 12:00 in returned result. The tokens are specified Time Format Tokens below format defined by the {DefaultDateFormat} setting in configure
    date="date" List of dates separated by comma.
    If delta is a positive number the latest of the dates is used.
    If delta is negative the earliest date is used.
    The dates can be in any format defined in System/TimeSpecifications (time is ignorred), or it can be the name of a TimeCalcPlugin storage name prefixed by a '$'. E.g. $myvar
    today
    delta="number of days" Days can be positive for the future or negative for the past 0
    holidays="list of dates" comma separated list of dates. The dates can be in any format defined in System/TimeSpecifications none
    store="variablename" Name of a variable in which the calculated date is stored. This variable can be used in another TimeCalcPlugin macro as an input date none
  • Example: %ADDWORKINGDAYS{"$year-$mo-$day date="23 Nov 2010" delta="25" holidays="24 Dec 2010, 25 Dec 2010, 01 Jan 2011"}%
  • Note: When adding working days the start day is not included. The resulting enddate is included.